Brain Teaser – May 25

Dr. Johnson needs to paint his clinic.

He knows that the painting job can be completed by 5 painters in 26 days.

If 15 more painters join the team 6 days after starting work on the job, then how many more days are required to complete the job?

See the answer

Answer:

5 more days. If 5 painters can do the job in 26 days, then   5 × 26 = 130 man-days are required.
When  5 painters work for 6 days, it makes  5 × 6 = 30 man-days.
The job still requires 130 − 30 = 100 man-days, and there are 20 painters available to do it.
20 painters for 100 man-days = 100 / 20 = 5 days.
Therefore, 5 more days are required to complete the painting job.

RELATED ARTICLES

Brain Teaser

Brain Teaser

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest News and Articles

SUBSCRIBE TO OUR NEWSLETTERS

Stay Connected
10,288FansLike
820FollowersFollow
249FollowersFollow
2,787FollowersFollow

Article of the month

Weight loss drug Tirzepatide helps beat heart failure

New drug, tirzepatide, shows promise for patients with diastolic/preserved ejection fraction heart failure. Find out more with MNB.

Joke Of The Day – February 15

Patient to his psychologist:When I hear my clock alarm in the morning, I feel like I got shot. And you get up right away? ...

ADVERTISE WITH US

error: Content is read-only and copy-protected.