Dr. Johnson needs to paint his clinic.

He knows that the painting job can be completed by 5 painters in 26 days.

If 15 more painters join the team 6 days after starting work on the job, then how many more days are required to complete the job?

See the answer

Answer:

5 more days. If 5 painters can do the job in 26 days, then   5 × 26 = 130 man-days are required.
When  5 painters work for 6 days, it makes  5 × 6 = 30 man-days.
The job still requires 130 − 30 = 100 man-days, and there are 20 painters available to do it.
20 painters for 100 man-days = 100 / 20 = 5 days.
Therefore, 5 more days are required to complete the painting job.

RELATED ARTICLES

Brain Teaser

Brain Teaser

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest News and Articles

SUBSCRIBE TO OUR NEWSLETTERS

Stay Connected
10,288FansLike
820FollowersFollow
249FollowersFollow
2,787FollowersFollow

Article of the month

Vitamin D as an Anti Colorectal Cancer Agent in 2024 – a Review of the Evidence

Vitamin D has a protective effect against colorectal cancer, but it is patient and population dependent.According to the WHO, colorectal cancer (CRC) is the...

Joke Of The Day- June 13

After 20 hours in delivery, a woman changes her mind and decides to go home. Doctor: This is the first time I have seen a...

ADVERTISE WITH US

error: Content is read-only and copy-protected.